Nevada Supreme Court Clarifies Mechanic and Materialman Lien Issues

By:  Nathan Kanute and Bob Olson

On August 7, 2014, the Nevada Supreme Court issued two opinions dealing with the priority of mechanics’ liens and the proof required for a materialman to establish a lien.  These cases provide valuable guidance to lenders, materialmen, contractors, and subcontractors operating in Nevada.

In Byrd Underground, LLC v. Angaur, LLC, 130 Nev. Adv. Op. 62, the United States Bankruptcy Court for the District of Nevada certified three questions to the Nevada Supreme Court.  The questions focused on whether placement of fill materials and grading constituted “construction of a work of improvement” for purposes of a lien priority determination under NRS 108.225. … Read More »

Author: Nathan Kanute | Leave a comment Tagged , ,